Ayesha Rahman

Back

VR/98-KAJANG/MR-0245

Approved

ATS Industrial Park (MBW) · created 5/1/2026 by ATS Import

Approval chain
Est. $421
  1. Level 1· Project Director (PD)

    sequential
    final tier
    • Ayesha Rahman
      Mandatory
      Approved
    Queued

Request header

One row per material. Expand to see line-level requested dates, fulfillment split, and (in edit mode) per-line edits.

MaterialUnitLinesRequestedNew purchaseTransferPO'd / OutST'd / OutEarliest
Check & Service Fire Extinguisher
HSE-Fire-Ext-Service
Nos21313013 / 00 / 02026-05-04

No comments yet.

No site transfers raised for this MR yet.

  • SI00119688
    PO
    2026-05-08 · Site Receiver
  • SI00119688
    PO
    2026-05-08 · Site Receiver