VR/98-KAJANG/MR-0378
Approved
ATS Industrial Park (MBW) · created 6/6/2026 by ATS Import
Approval chain
Est. $741,500
Level 1· Project Director (PD)
sequentialfinal tier- Ayesha RahmanMandatoryApproved
Queued- Ayesha Rahman
Request header
One row per material. Expand to see line-level requested dates, fulfillment split, and (in edit mode) per-line edits.
| Material | Unit | Lines | Requested | New purchase | Transfer | PO'd / Out | ST'd / Out | Earliest | |
|---|---|---|---|---|---|---|---|---|---|
Concrete G30N CONC-G30N | m3 | 1 | 500 | 500 | 0 | 500 / 0 | 0 / 0 | 2026-06-12 | |
Concrete G30T1 CONC-G30T1 | m3 | 1 | 500 | 500 | 0 | 500 / 0 | 0 / 0 | 2026-06-12 | |
Concrete G35N CONC-G35N | m3 | 1 | 500 | 500 | 0 | 500 / 0 | 0 / 0 | 2026-06-12 | |
Concrete G35P CONC-G35P | m3 | 1 | 500 | 500 | 0 | 500 / 0 | 0 / 0 | 2026-06-12 | |
Concrete G35T1 CONC-G35T1 | m3 | 1 | 500 | 500 | 0 | 500 / 0 | 0 / 0 | 2026-06-12 |
No comments yet.
- VR/98-ATS Industrial Park(MBW)\N478Issued6/12/2026· Concrete
No site transfers raised for this MR yet.